All hollow-core slabs needed for Bamako No.3 Bridge undertaken by CGGC prefabricated

Updated: 2010-10-17

On Oct 13, the concreting for the last hollow-core slab was finished in the prefabrication plant on the north side of Bamako No.3 Bridge undertaken by CGGC.

The total length of the Bamako No.3 Bridge project is 2294.181 meters, including 1625.5 meters for the body of the bridge. Consecutive box girders for three main parts of the bridge are cast in-situ, but beams and slabs for other parts are prefabricated, including 70 T-shape beams and 954 hollow-core slabs.

 